Tuesday, June 5, 2012

Retaining Wall Renovation: Part 2- Preparations

Starting about a month ago, Roger had to make a list of all the materials we were going to need. He had to measure and calculate the number and type of stones, the equipment and tools, the food (ok, I did that), and the time it was going to take.

Here's his list:


Building Material
Bricks                 $5.55 0 $0.00
Caps                 $5.55 0 $0.00
Pins                    $0.34 0 $0.00
2a mod (ton)            $23.75 0 $0.00
2b washed (ton) $25.00 0 $0.00
Geogrid
Surebond Glue
Versalifter Rental      $35.00 3 $105.00

Total 1         $2,870.45

Dumpster Rental
10 Ft $285.00 1 $285.00

Equipment
Wheelbarrow         $35.00 1 $35.00
Tamper (per day) $55.00 2 $110.00
Dingo (8 hours)         $105.00 6 $630.00

Other
Pallet Charge         $15.00 13 $195.00
Pallet Return         $15.00 -13 -$195.00

Delivery (Bricks) $220.00 1 $0.00
Delivery (Stone) $25.00 0 $0.00

Food                 $300.00 1 $300.00


Total $4,335.45